I just got back from the post office, the IPR form has been sent to Nationwide Disc! We're just about ready to go!
So just to do some quick estimates.... supposing the masters and IPR arrive on Monday, it will take 24-48 hours for the project manager to look over and confirm all the details with me. If that all goes well, lets assume manufacturing takes place the next day, March 8th, and from there it will take 10 business days to produce (so excluding Saturday and Sundays), which would end on March 22nd. After production it will take around 3 days to ship here, so everything might be ready by Monday, March 26th.
This is based off a lot of guesstimation, there's a lot of factors involved. If we're lucky, it might arrive sooner, hopefully in time for the MGC. Or the confirmation process might take longer than expected, so it could arrive later. I'll update the progress here.